Advance payment bond for construction contracts
If the client agrees to make an advance payment (sometimes referred to as a down payment) to a supplier, a bond may be required to secure the payment against default by the contractor. This is referred to as an advance payment bond (APB), advance payment guarantee or advance stage payment.
For more information, see Advance payment.
Typically on a construction project an advanced payment bond will be required by the client if the contractor requests advance payment to help them meet significant start up or procurement costs that may have to be incurred before construction begins.
For example, where the contractor has had to purchase high-value plant, equipment or materials specifically for the project. The bond will protect the client in the event that the contractor fails to fulfil its contractual obligations, for example if the contractor becomes insolvent.
An advance payment bond will normally be an on-demand bond, meaning that the bondsman pays the amount of money set out in the bond immediately on demand, without any preconditions having to be met. This is as opposed to a a conditional bond (or default bond) where the bondsman is only liable if it has been established that there has been a breach of contract.
Advance payment bonds must be very carefully drafted to set out the circumstances for payment and to make clear that they are on-demand bonds.
A ‘vesting certificate’ or ‘certificate of vesting’ may be required from the contractor (or sub-contractors or suppliers), certifying that ownership of goods, plant or materials listed in a schedule will transfer from one party to the other upon payment and confirming that they will be properly identified, separately stored, insured and are free from encumbrances (such as retention of title).
For more information see: Vesting certificate.
[edit] Related articles on Designing Buildings
- Advance payment.
- Bid bond.
- Bonds in construction contracts
- Bonds and guarantees.
- Escrow.
- Materials on site.
- Off-site goods and materials.
- Off-site goods and materials - legal issues.
- On-demand bond.
- Parent company guarantee.
- Performance bond.
- Retention.
- Retention bond.
- Vesting certificate.
- Wuhan Guoyu Logistics Group Co Ltd & Anr v Emporiki Bank of Greece SA.
- Zero-coupon bond.
[edit] External references
- Rainy Sky S.A. v Kookmin Bank.
Featured articles and news
Scottish Government action to reach net-zero targets
Retrofit expert group highlight critical actions needed.
A forward thinking, inclusive global community of members.
From engineered product life-spans, to their extension.
Circular economy in the built environment
A brief description from 2021. Where are we now?
Mental Health Awareness Week with ABS
Architects Benevolent Society programme of activity.
CLC publishes domestic retrofit competency framework
Roadmap of Skills for net zero.
May 13-19: Moving more for our mental health.
Understanding is key to conservation.
Open industry engagement survey seeks responses
Institutions and the importance of engagement.
National Retrofit Hub unveils new guide
Digital Building Logbooks and Retrofit: An Introduction.
Enhancing construction site reporting efficiency
Through digitisation and the digital revolution.
Noise in the built environment
BSRIA guide TG 20/2021.
17,000 people suffer conditions as a result of exposure to excessive noise at work.
Turning down the noise: Auditory health
A pervasive risk with far-reaching consequences.
Getting the most out of heat pumps and heating
How heat pumps work and how they work best.
Electrotechnical excellence, now open for entries.
Comments